Estimating Small Project Costs

Estimate materials, quantities, waste and contingency.

Understanding the topic

A project estimate combines quantities, unit prices and other costs such as delivery or tool hire. Estimates are approximate and should include a reasonable allowance for waste and unexpected work.

Use the examples below as a starting point, then adapt the method to your own situation.

Step-by-step approach

Measure the job; calculate materials; check pack sizes; add delivery and consumables; include contingency; compare with the budget.

  1. Identify the purpose and information you need.
  2. Follow the recommended method carefully.
  3. Check your result against the original purpose.
  4. Revise anything unclear or incomplete.

Examples at a glance

SituationExampleExplanation
PaintNeed 7 L; paint sold in 4 L tins.Buy two tins for 8 L, subject to coverage and coats.
TilesFloor is 12 m²; allow 10% extra.Plan for about 13.2 m² before rounding to pack quantities.
MaterialsTimber $85, fasteners $18, delivery $25.Subtotal is $128 before contingency.
ContingencyEstimated job cost $400; allow 15%.Contingency $60; planning total $460.

Four worked examples

Example 1: Paint

Starting point: Need 7 L; paint sold in 4 L tins.

Why this works: Buy two tins for 8 L, subject to coverage and coats.

Example 2: Tiles

Starting point: Floor is 12 m²; allow 10% extra.

Why this works: Plan for about 13.2 m² before rounding to pack quantities.

Example 3: Materials

Starting point: Timber $85, fasteners $18, delivery $25.

Why this works: Subtotal is $128 before contingency.

Example 4: Contingency

Starting point: Estimated job cost $400; allow 15%.

Why this works: Contingency $60; planning total $460.

Common mistakes

  • Ignoring pack sizes or minimum order quantities.
  • Using measurements from memory rather than checking.
  • Forgetting taxes, delivery or waste allowances.

Practice questions

Think about your answer, then expand each question to compare.

Question 1: What is the main purpose of estimating small project costs?

A project estimate combines quantities, unit prices and other costs such as delivery or tool hire. Estimates are approximate and should include a reasonable allowance for waste and unexpected work.

Question 2: What is a useful first step?

Measure the job; calculate materials; check pack sizes; add delivery and consumables; include contingency; compare with the budget.

Question 3: How would you handle this situation: Paint?

Buy two tins for 8 L, subject to coverage and coats.

Question 4: What does this example teach: Timber $85, fasteners $18, delivery $25.?

Subtotal is $128 before contingency.

Question 5: Name one mistake to avoid.

Ignoring pack sizes or minimum order quantities.

Review checklist

  • Can you explain the main idea in your own words?
  • Can you apply the method to a new example?
  • Have you checked the relevant facts, figures and instructions?
  • Can you identify a common mistake and avoid it?